Mayor Restaino Now Wants Feasibility Study to See if He Still Wants to Take NFR Land

N
Niagara Reporter-  ·  April 24, 2024
Mayor Restaino Now Wants Feasibility Study to See if He Still Wants to Take NFR Land
SharefXin

This is not how eminent domain is supposed to work.

It is also not how development is supposed to work, even when, like Niagara Falls Mayor Robert Restaino, you’re spending taxpayers’ money.

Mayor Restaino told his Buffalo lawyers to tell the NY State Supreme Court that 10 acres of private property on John B. Daly Blvd. owned by Niagara Falls Development LLC., is the only suitable land on which he could build his unfunded event center, “Centennial Park.”

Artist rendering of “Centennial Park” project

That appears to be untrue.

Restaino has not yet determined whether the property is even right for the Centennial Park project after all. But that did not stop him from halting NFR’s plans to build a $1.5 billion Data Center – which would employ 550 people in good-paying jobs and position the City to be in on the cutting edge of the high tech industry.

It was already outrageous that Restaino singled out 10 acres of land in the heart of NFR’s planned 60-acre mega development to build a middling arena and a parking ramp, which nobody is even certain will be used if he can get the taxpayer money to build it.

Mayor Robert Restaino

It is now nearly two years since Mayor Restaino stopped the NFR project ————————— by suing the owners through the legal process of eminent domain to begin his ill-advised pursuit of NFR’s land on John B. Daly Blvd. for his speculative, unfunded event center scheme, “Centennial Park.”

But after blocking the project that would not cost taxpayers a dime, which would bring needed jobs and tax revenue and spending an untold amount on Buffalo lawyers to sue NFR, Restaino now says he wants to spend more taxpayer money to do something he should have done from the start. – do a feasibility study to determine the best location for Centennial Park.

In fact, Restaino’s makes it clear that NFR’s property – referred to as Parcel 0 by the company is “just one of numerous potential locations for a potential Centennial Park.”

A proper study will very likely determine that there are better locations: closer to small businesses and other commercial establishments, and on government-owned land that saves city taxpayers acquisition costs entirely.

Restaino launched his attempt to take NFR’s land in mid-2022, even after working with NFR and Toronto developer Urbacon on the same parcel of land—before suddenly deciding to take the land for his speculative arena.

Restaino now proposes to spend $140,000 on a feasibility study to figure out if NFR’s land is right.

At the end of the day, the Mayor admits he has no plan for funding the hundreds of millions of dollars it will take to actually build an arena, parking ramp and a tiny park.

His attitude, which comes easy if one is not spending his own money, is “if we propose it, they will come” approach, saying that once the city gets the land, the state and federal funding will appear.

The Mayor hasn’t pointed to a single example where another project of this size and type in New York State has been funded in a similar manner.

Even the funding for the feasibility study appears to be money the City of Niagara Falls doesn’t have.

The Mayor’s recent communication to the City Council states that the funds will come from (1) a grant from National Grid; (2) state money from Empire State Development (ESD) (through Niagara USA), and—significantly—“funding available from American Rescue Plan using Treasury Guidance Expenditure Category 6.1, which is “Revenue Replacement for the Provision of Government Services.”

As only $70,000 came from ESD, we can assume a large sum will be taken from the American Rescue Plan—money that was earmarked to help the city recover from the COVID-19 pandemic.

This money cannot be used legally to fund a feasibility study on an arena.

This money was not intended to be used for a feasibility study for an arena.

This was never the purpose of these funds, and every dollar spent on a feasibility study is money that could be used for roads, water and sewer infrastructure, public health services, small businesses and non-profits, broadband infrastructure, and all of the other uses specifically named in the Treasury Department guidelines.

The Treasury Department guidelines do not reference to a study to determine the feasibility of speculative arena as an acceptable use of funds.

In her last three budgets, Governor Kathy Hochul has earmarked zero dollars for Centennial Park, despite the fact that the City of Niagara Falls has been paying one of the most prominent lobbying firms in New York State for several years to lobby on Mayor Restaino’s behalf.

Even if the Mayor’s supposed $150 million project is built, reports indicate it will never operate at a profit. According to a September 2022 report by the Niagara University’s Global Tourism Institute, a 2017 arena development analysis commissioned by the Niagara County Legislature and generated by the Minneapolis-based consulting firm Convention, Sports & Leisure considered two potential options for running a “multi-use hybrid venue” in the Falls that could accommodate crowds of between 4,000 and 6,000 people.

  • The “tenant model,” which would involve at least one anchor tenant such as Niagara University’s hockey or basketball programs, had the potential to attract 108 events and 184,500 attendees per year. That option came with an annual financial loss estimate of $261,000.
  • The “non-tenant model,” which considered an arena that did not have an anchor tenant such as NU, had the potential to attract 98 events and 148,250 attendees per year. That option had the potential to run at an annual loss at $482,000 per year.

 Who pays for the losses? City taxpayers do!

Can City of Niagara Falls taxpayers really afford this? Consider the following, from the same report:

“…the city government spends an average of $90 million per year, but it has just $75 million in annual revenue. It has ‘made ends meet’ over the past two decades by using ‘casino money.’”

All of this points away from the project. But the Reporter knew this two years ago, before this incompetent Mayor spent an unknown amount of money – diverted from the city – to stop what could be a world class Data Center that could be a game changer.

And now he is not sure he even wants the land.

SharefXin

Comments (0)

Leave a comment

More From Niagara Falls Reporter

Niagara Falls Hosts Oldest State Park But State Needs to Provide More Assistance
Featured

Niagara Falls Hosts Oldest State Park But State Needs to Provide More Assistance

By tony Farina · August 26, 2026

By Tony Farina The Niagara Falls State Park, located in Niagara Falls, N.Y., and created in 1885, is recognized as the oldest state park in the U.S. and contains the American Falls, the Bridal Veil Falls, and a portion of the Horseshoe Falls (also known as the Canadian Falls). Following a $44-million refurbishment of the 221-acre park in 2003, in 2007 it was named the 10 th most beautiful spot in America by “The Today Show.” According to the state’s Office of Parks, Recreation, and Historic Preservation, the State Park receives more than nine million visits each year. It is

Featured

WEBR to Launch Katie Daye Show on Monday

By tony Farina · August 21, 2026

By Tony Farina There is much excitement in the airwaves at WEBR The Breeze as station manager and program director Frank Miller has announced that beginning on Monday, Aug. 24, the talent he has been hoping to bring in for some time will be joining the WEBR midday lineup from 10 a.m. to 2 p.m. every weekday. “We’re just thrilled to be launching the Kadie Daye show on Monday, and we are so looking forward to having a talent like Kadie on our airwaves at WEBR AM 1440, FM 105.3 and FM 106.9,” Miller said in talking about the new

Far Too Often, Promises Have Proved Empty; Niagara Falls Needs Progress And Strategic Planning
Featured

Far Too Often, Promises Have Proved Empty; Niagara Falls Needs Progress And Strategic Planning

By tony Farina · August 4, 2026

By Tony Farina Promises are nice and they bring hope for the future. But unfortunately, most of the time, promises have fallen flat for the City of Niagara Falls, some succeeding but many turning out to be empty promises and major disappointments. At this point, Niagara Falls doesn’t need more failed promises. What the city needs is progress to build a better future and a plan to make it work. City leadership must bring it all together. While there are promises to build a better future on the table and being talked about, like Centennial Park and the Niagara Digital

Governor Issues Response To McMurray’s Letter on Slag Concerns
Featured

Governor Issues Response To McMurray’s Letter on Slag Concerns

By tony Farina · August 4, 2026

By Tony Farina The radioactive slag bubbling up across Niagara County in recent weeks, triggering state and federal testing and some remedial work and family relocations, is the ongoing and seemingly never-ending legacy of the environmental desecration of the past 100-plus years by massive corporations dumping toxic waste that was the subject of Christen Civiletto’s book Thundering Waters. “What we have again is an environmental storm,” said attorney and former Grand Island Supervisor Nate McMurray, a candidate for election to the 45th District State Assembly seat now open because of the retirement of Angelo Morinello. McMurray will run for the